Home>To-Do Lists>Fall Semester 2004> December 12 2004


  Weekly To Do List:
        

To-Do List for the week of December 12 2004

Activity
Assigned to
Assigned Date
Due Date
Status
Remarks
Add narrative of work done to the ERS document and format Ruchi
Dec 7
Dec 12
Handed to David for final review.
Finalize the ERS document and format David
Dec 9
Dec 15
Signed by the client and submitted on Dec 14- Deadline met successfully.
Initial design of MGX in integrated mode Namita
Dec 02
Dec 14
Scope limited further to Protex only after the client meeting
 