Home>To-Do Lists>Spring Semester 2005> May 08 2005


To-Do List

 

Week of May 8th, 2005

Activity
Assigned
To
Assigned
Date
Due_Date
Status
Remarks
GeneX: "diff" algorithm. Ruchi Feb 22 Apr 12
There is still some work to do, but the feature exists. Final work completed on May 10.
Protex:Implement changes as per client request Namita
David
Mar 10 May 17
3 out of 5 changes implemented.
Installer: Add license.  Put things in right folders on Install.  Clean up mess on Uninstall.
Pradeep Apr 22
May 17
Due date postponed from Mar.
Convert Protex and VGL use cases to xml
David Mar 29
May 17
Due date postponed from Mar.
Test, add bugs at Sourceforge database, remove high priority bugs
Team
Apr 19
May 17
Due date postponed from Feb.; Namita took over task assign. from David on 29 March.
Use-case reviews. Ruchi
Pradeep
David
Mar 29 May 17
Due date postponed from Mar.

Make all JAR files;  Put them on the release page.

Namita May 10 May 17 One step build.
Clean CVS directories, add README. Team May 3 May 17 Old releases and redundant copies removed.
Update webpages: Risks, Milestones, To-Do's, deliverables. Ruchi May 10 May 17
Updated to reflect the current status.
Project Report
Ruchi
May 10 May 17
Report to be indexed by Namita and reviewed by David.
Website update David
Jan 27 May 21 - David will write Meeting Minutes and update To-Do Lists. David or Ruchi will write the To-Do Lists; Ruchi will approve them.
 
 