To-Do List for the week of September 30 2004
Activity |
Assigned to |
|
|
Status |
Remarks |
Draft a letter to client |
Ruchi |
Sep 30 2004 |
Oct 6 2004 |
|
|
Prepare risk analysis draft |
Ruchi |
Sep 30 2004 |
Oct 3 2004 |
|
Effort done by the team |
Prepare initial thoughts drafts |
Ruchi |
Sep 30 2004 |
Oct 3 2004 |
|
Effort done by the team |
Design logo |
Pradeep |
Sep 30 2004 |
Oct 3 2004 |
|
Effort done by the team |
Find a suitable project name |
Ruchi, Namita |
Sep 30 2004 |
Oct 7 2004 |
|
|
Prepare for presentation to team about basic terminologies |
Namita |
Sep 30 2004 |
Oct 3 2004 |
|
|
Initial design of webpage draft |
Pradeep |
Sep 30 2004 |
Oct 3 2004 |
|
|